33 permits
- Records on file
- 33
Built (as contractor)
33 entries
- Issued Oct 14, 2026
Addition and/or Alteration · Install 200A service head, 200A service cable, 200A CT cabinet - Install 200A main panel, 30KVA step down tranformer from 240 to 208V - Install 70A, 120/208 3 phase breaker and terminate to bakery oven.
- Issued Oct 1, 2026
Addition and/or Alteration · Install 1 light switch, 2 light fixtures and 3 duplex receptacles
- Issued Sep 30, 2026
Addition and/or Alteration · Rewire entire house according to NEC : install duplex receptacles, AFIC/GFICs breakers. Light fixtures, install 240V, 40A for condenser unit and 120V for furnace, single lines for kitchen outlet. one outdoor GFIs receptacle
- Issued Sep 23, 2026
Addition and/or Alteration · Install 200A services and rewire nail salon throughout, including installation of lighting fixtures, switches, and receptacle outlets. Install interconnected smoke and carbon monoxide alarms. Furnish and install a complete fire alarm system, including all required devices and wiring. (2nd floor apartment is not included in the scope of work.) All work shall be performed in accordance with the 2017 NEC, 2016 NFPA 72 and the approved plans.
- Issued Sep 22, 2026
Addition and/or Alteration · Increasing to a 200A service, one meter socket, 200A service cable and service head 1- 200A main panel. Rewire entire house according to NEC : install duplex receptacles, AFIC/GFICs breakers. Light fixtures, install 240V , 40A for condenser unit and 120V for furnace, single lines for kitchen outlet. one outdoor GFIs receptacle. install the outdoor light in front and back.
- Issued Sep 17, 2026
Addition and/or Alteration · INTERIOR RENOVATION TO EXISTING 2-STORY SEMI-DETACHED SINGLE FAMILY DWELLING. WORK INCLUDES TO REPLACE KITCHEN AND 2ND FLOOR BATHROOM, AND INSTALL NEW FINISHES THROUGHOUT. NEW BATHROOM AT THE FIRST FLOOR FRONT.PROPOSED REPLACEMENT OF FRONT CONCRETE SLAB. DETAILS AS SHOWN IN THE PLAN. NO STRUCTURAL WORK. SEPERATE PERMIT REQUIRED FOR COMPLYING THE VIOLATION # CF-2026-104286 ( SHED ADDITION)
- Issued Jul 31, 2026
Addition and/or Alteration · Replace crown heater with new electrical base heater
- Issued Jul 22, 2026
Addition and/or Alteration · install 120v, 20A line for condenser, outdoor 20A GFIC duplex s with receptacle, 10 light fixtures, 5 light switches, 2 flood lights,
- Issued Jul 21, 2026
Addition and/or Alterations · EZ PERMIT DUCTWORK & WARM-AIR APPLIANCES- For the installation of New Ductwork, Registers/Grilles/Diffusers, and Warm-Air Appliances as per attached standards. Deviations from these standards require submission of construction and site plans. Replace the existing with the same type, Gas Boiler 80% AFUE, 100,000 BTU, NO NEW DUCTWORK IS PART OF THIS PERMIT, APPLIANCE REPLACEMENT LIKE IN KIND ONLY.
- Issued Jul 17, 2026
Addition and/or Alterations · EZ PERMIT DUCTWORK & WARM-AIR APPLIANCES - For the installation of New Ductwork, Registers/Grilles/Diffusers, and Warm-Air Appliances as per attached standards. Deviations from these standards require submission of construction and site plans. Install 2 ton ductless mini split system with heat pump, 1 heat pump condenser, and 1 wall mount air handler (evap).
- Issued Jul 6, 2026
Addition and/or Alteration · Upgrade to 400 amp electrical service with 3 meter socket and proper grounding and bonding. All work to be done according to the 2017 NEC and per approved plans.
- Issued Jun 1, 2026
Addition and/or Alterations · EZ PERMIT DUCTWORK & WARM-AIR APPLIANCES - For the installation of New Ductwork, Registers/Grilles/Diffusers, and Warm-Air Appliances as per attached standards. Deviations from these standards require submission of construction and site plans. Installation of Fuel Gas piping as per IFGC.
- Issued May 19, 2026
Addition and/or Alteration · Install 1000A service, 120/208 V 3 phases, 1 -200A CT cabinet, 4- meter sockets (200A and 3- 150A) and one CT and 400 amp disconnect. Install light switches and fixtures. GFICs/AFICs breakers and duplex receptacles as plan attached and 2020 NEC. Install fire alarm system ( 1 FACP, smoke and heat detectors, horns/strobes, pull stations as per 2019 NFPA 72.
- Issued May 9, 2026
Addition and/or Alteration · Electrical Permit for combo RP-2025-005191
- Issued May 6, 2026
Addition and/or Alteration · Re-wire whole house with 200 amp service cable, new light switches, outlets and smoke detector using fishing method.
- Issued Feb 20, 2026
Addition and/or Alteration · Electrical Permit for combo CP-2025-005756
- Issued Jan 30, 2026
Addition and/or Alterations · Mechanical / Fuel Gas Permit for combo RP-2025-011388
- Issued Jan 30, 2026
Addition and/or Alteration · Electrical Permit for combo RP-2025-011388
- Issued Jan 28, 2026
Addition and/or Alteration · Install 200A service: 1 meter sockert, 200 Amp main panel, service cable and terminate ground wire from water meter and Rods to main disconnect
- Issued Jan 23, 2026
Addition and/or Alteration · nterior rewire light fixtures, switches, duplex receptacles, GFICs and AFICs.
- Issued Dec 31, 2025
Addition and/or Alteration · Using the existing 120A panel, interior wiring (refer to equipment schedule). install light fixtures, duplex receptacles, breakers, GFICs.
- Issued Dec 11, 2025
Addition and/or Alteration · Repair rear exterior walls and replace existing deck in kind only. details as shown on the plan. no other work included. see RP-2022 -006924 for other work details.
- Issued Dec 9, 2025
Addition and/or Alteration · Electrical Permit for combo RP-2025-012142
- Issued Dec 7, 2025
Addition and/or Alteration · Install new 200 amp service, rewire light switches, install smoke detectors and outlets per 2017 NEC code. Install wire using fishing method.
- Issued Dec 5, 2025
Addition and/or Alteration · Replace 3 pull station4, 6 smoke detector, 5 horn/strobes, one FACP. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC AND 2016 NFPA 72.
- Issued Dec 5, 2025
Addition and/or Alteration · Remove and replace the existing light fixture with LED lights. Input 120V, 20A line that feet to 60W power supply to feed LED light at 2-60W, 12V.. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC. BUILDING PERMIT GP-2025-008158
- Issued Nov 13, 2025
Addition and/or Alteration · Electrical Permit for combo CP-2024-001293
- Issued Oct 28, 2025
Addition and/or Alteration · Replace/install 200A, 120/240v, single phase service, recessed lights, duplex receptacles, AFICs and GFICs, switches, ceiling fans.
- Issued Sep 26, 2025
Addition and/or Alteration · Electrical Permit for combo RP-2025-008616
- Issued Sep 24, 2025
Addition and/or Alteration · INTERIOR ALTERATIONS TO AN EXISTING ATTACHED STRUCTURE USED AS A SINGLE-FAMILY DWELLING AS PER BUILDING APPLICATION/PLAN.
- Issued Aug 14, 2025
Addition and/or Alteration · Replace/install 200A service only: 200A meter sockets, 200A main panel, install ground wire from water meter and Rods to main disconnect
- Issued Jul 31, 2025
1 units
Addition and/or Alteration · PERMIT- For (Repair roof from Cottman Ave incident) to resolve case #CF-2025-007443. Abutting sidewalk must be closed with fencing a minimum of 6’ in height. Separate Streets Department permit required for sidewalk closure. A separate permit is required for any additional alterations that are not specifically addressed on case #CF-2025-007443. “In accordance with Code Bulletin PM-1801, a PA professional engineer is required to monitor repairs made under this permit. The engineer must submit a s
- Issued Jul 31, 2025
Addition and/or Alteration · Install fire alarm system as per 2016 NFPA 72.
Track this owner
We'll flag their next deal, permit, or filing — usually before the neighbors know.
Entities are grouped by a normalized name from the public record; a separate legal entity per building is common, so some portfolios span several related names. Sources: Phila. Dept. of Records (deeds), L&I (permits & violations), Dept. of Revenue (tax delinquencies), reflecting the record as of our last weekly ingest. Verify independently before relying on it.
Last generated November 4, 2026.