THE INDEX: 64 17 · week of Jun 29permits soft, openings quiet, deal ledger quiet

The Philadelphia Index

Entity File · The Public Record

Company / LLC

Waybar Construction LLC

10 permits

Records on file
10

Built (as contractor)

10 entries

  1. Issued May 21, 2026

    1 units

    516 S 17th St

    New Construction · ERECTION OF AN ATTACHED STRUCTURE FOR USE AS SINGLE-FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN EXCAVATION PERMIT AND GEO TECH REPORT. SEPARATE PERMITS REQUIRED FOR ELECTRICAL, MECHANICAL, PLUMBING AND SPRINKLER (13D) WORK. UNDERPINNING IS not PART OF THIS PERMIT . ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C.O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY.

  2. Issued Feb 17, 2026

    12 units

    1808 Wylie St

    New Construction · NEW CONSTRUCTION OF A FOUR (4) STORY BUILDING WITH CELLAR AND PRIVATE ROOF DECKS WITH PILOT HOUSES FOR USE AS TWELVE (12) DWELLING UNITS WITH ACCESSORY PARKING AS PER APPROVED PLANS. SEE SP-2025-001052 FOR ASSOCIATED EXCAVATION WORK. BUILDING TO BE FULLY SPRINKLERED PER NFPA 13 AND INCLUDE STANDPIPES PER NFPA 14. FIRE WATCH REQUIRED PER CODE BULLETIN F-2001. *2018 IBC* **SEPARATE PERMITS REQUIRED FOR MEP & FIRE SUPPRESSION WORK** AMENDMENT APPROVED 3/28/26 AMEND NEW CONSTRUCTION PERMIT CP-2025

  3. Issued Jan 21, 2026

    1 units

    518 S 17th St

    New Construction · ERECTION OF AN ATTACHED STRUCTURE FOR USE AS SINGLE-FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN EXCAVATION PERMIT AND GEO TECH REPORT. SEPARATE PERMITS REQUIRED FOR ELECTRICAL, MECHANICAL, PLUMBING AND SPRINKLER (13D) WORK. UNDERPINNING IS PART OF THIS PERMIT WITH CONTINUED INSPECTIONS. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C.O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVE

  4. Issued Jan 8, 2026

    1 units

    1915 Fitzwater St

    New Construction · Amend Permit 4/21/2026 reconfiguration of cellar to work with the existing condition of the adjacent rowhouse. Work to include revised excavation and foundation wall. No Increase in excavation Depth. ERECTION OF AN ATTACHED STRUCTURE FOR USE AS SINGLE FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEO TECH REPORT. SEPARATE PERMITS REQUIRED FOR SPRINKLER (13D) WORK. (UNDERPINNNING IS NOT PART OF THIS PERMIT). ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE

  5. Issued Dec 11, 2025

    1 units

    214 S 11th St

    Addition and/or Alteration · FOR LEVEL II WORK AT FRONT FACADE TO REPLACE EXISTING WINDOW WITH NEW WINDOW AND DOOR FRAME IN EXISTING OPENIND. FOR USE AS VACANT COMMERCIAL AT FRONT OF FIRST FLOOR AND VISITOR ACCOMODATIONS (SIX UNITS) ON FIRST THROUGH FOURTH FLOORS. AS PER APPROVED PLANS.

  6. Issued Dec 9, 2025

    1 units

    159-63 Laurel St

    New Construction · FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS A SINGLE-FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY.

  7. Issued Nov 17, 2025

    1808 Wylie St

    Foundation · FOR FOUNDATION WORK AS PER APPROVED PLANS. SEE SP-2025-001052 FOR EXCAVATION PLANS.

  8. Issued Oct 31, 2025

    319 S 18th St

    Addition and/or Alteration · Level III interior alterations to an existing attached structure include construction of roof access structure with roof deck, removal and replacement of basement slab with no excavation and no change of ceiling height. Removal of chimney and stucco of existing adjacent chimney. PHC Staff Review of window assembly 'shop' drawings required for final approval. PHC Staff Review of masonry pointing sample in the field required for final approval. PHC Staff Review of masonry cutout sample in the fi

  9. Issued Oct 2, 2025

    1 units

    524 S 17th St

    New Construction · FOR THE ERECTION OF AN ATTACHED STRUCTURE FOR USE AS SINGLE-FAMILY HOUSEHOLD LIVING. SHEETING AND SHORING AS PRESCRIBED IN GEOTECH REPORT. (UNDERPINNING NOT A PART OF THIS PERMIT). SEPARATE PERMITS REQUIRED FOR SPRINKLER (NFPA 13D) WORK. ENERGY CODE COMPLIANCE IN ACCORDANCE WITH 2018 IECC. PRIOR TO ISSUANCE OF C/O SUBMITTAL OF AIR BARRIER CHECKLIST AND ENVELOPE TESTING CERTIFICATE IS REQUIRED. BOTH TO BE COMPLETED BY AN APPROVED PARTY. AMENDMENT #1: AMEND TO REVISE THE INTERIOR LAYOUT OF THE 2

  10. Issued Sep 3, 2025

    1 units

    1810 Bainbridge St

    New Construction · FOR THE INSTALLATION OF HELICAL PILES AND GRADE BEAM AT THE FOUNDATION WALL SHARED WITH 1810 BAINBRIDGE ST. AND FOR THE ERECTION OF A THREE (3) STORY ATTACHED STRUCTURE OF TYPE V-B CONSTRUCTION WITH BASEMENT, ROOF DECK, AND ROOF DECK ACCESS STRUCTURE FOR USE AS A SINGLE-FAMILY DWELLING (GROUP R-3). BUILDING TO BE FULLY SPRINKLERED WITH A MINIMUM NFPA 13D AUTOMATIC SPRINKLER SYSTEM. ALL WORK TO BE DONE PER APPROVED PLANS AND IN ACCORDANCE WITH 2018 IRC. SEPARATE PERMITS REQUIRED FOR MECHANICAL, E

Track this owner

We'll flag their next deal, permit, or filing — usually before the neighbors know.

Entities are grouped by a normalized name from the public record; a separate legal entity per building is common, so some portfolios span several related names. Sources: Phila. Dept. of Records (deeds), L&I (permits & violations), Dept. of Revenue (tax delinquencies), reflecting the record as of our last weekly ingest. Verify independently before relying on it.