Entity File · The Public Record
Company / LLC
Carr And Duff LLC
27 permits
- Records on file
- 27
Built (as contractor)
27 entries
- Issued Jul 2, 2026
Addition and/or Alteration · Power feeders & lighting installation for a new conveyor system. 100A power feeders at 2 locations. Wiring for area lighting ***ALL WORK PER APPROVED PLANS***
- Issued Jun 15, 2026
Addition and/or Alteration · Installation of 6 replacement pad-mounted transformers (5 - 1500kVA & 1 - 750kVA) . ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC.
- Issued Jun 15, 2026
Addition and/or Alteration · Refeed existing 200Amp, 240V, 1-Phase,3-Wire existing load center for parking lot lighting as per 2017 NEC.
- Issued May 25, 2026
Addition and/or Alteration · Provide all labor, material, equipment, and supervision for the intake pump electrical feed to run one (1) 3” SCH 40 PVC conduit plus one spare 3” SCH 40 PVC conduit from 50 FT. away from the pump to the pump and install one set of 4#350KCMIL and 1#4G 600V wire from the panel in the maintenance building to the pumps in accordance with Cobbs Creek Golf Course Restoration – Water Source plans (attached) and E1.00 Electrical Single Line Diagram and Details (attached) 200amp 208/120v as per 2017 NEC
- Issued May 13, 2026
New Construction · Install owner furnished medium voltage switchgear, MV switches, MV transformers, DC battery rack system, power panels, lighting, receptacles, FA devices, data devices, conduit, and cabling in the new substation building. all work per approved plans NEC 2017
- Issued May 12, 2026
Addition and/or Alteration · Temporary 200 amp single phase 120/240v service entrance for mobile cell site
- Issued May 6, 2026
Addition and/or Alteration · Provide (3) 200amp 3-Phase 120/208 main breaker panels and (1) Disconnect. Temporary Service will be feed from existing PECO pole #67169 with (3) existing PECO Pole Top 25KVA transformers from Maiden Lane which is located across the street from the temporary trailer complex. All work to be perform according to the 2017 NEC and per approved plans. SP-2026-000236
- Issued Apr 9, 2026
Addition and/or Alteration · 200 amp 1-Phase 120/240v Temp. Electrical Service for Jobsite Trailer.
- Issued Mar 18, 2026
Addition and/or Alteration · Disconnect & remove the existing disconnects and starters from the Mechanical and HVAC equipment. Install new Feeders to the mechanical-supplied disconnects, VFDs, and equipment. Disconnect existing Duct Detectors and install new Duct Detectors on the latest HVAC equipment. Remove existing Lighting fixtures & replace with new Lighting fixtures. All work in accordance with NEC & NFPA. All work Per approved plans
- Issued Mar 16, 2026
Addition and/or Alteration · Install underground duct bank and associated distribution equipment to serve the recreation park. Furnish and install the Musco sports lighting system, including poles, luminaires, wiring, and controls as part of the sports lighting package. Install a separate underground duct bank for telecommunications infrastructure. All work shall be completed in accordance with the approved plans and the 2017 NEC,
- Issued Mar 12, 2026
Addition and/or Alteration · Electrical Permit for combo CP-2025-005309
- Issued Feb 27, 2026
New Construction · Electrical Permit for combo SP-2023-000100
- Issued Feb 24, 2026
Addition and/or Alteration · New power to bridge crane Power for rollup door Power for Unit Heater Power for heat pumps Lightning Protection New Power to intake crane Temp electric as needed ***NO FIRE ALARM ON THIS PERMIT**
- Issued Jan 27, 2026
Addition and/or Alteration · 12th and Filbert Street tunnel lighting renovation and painting of underpass. Furnish and install 3/4'' GRS conduit, lighting circuits, lighting, lighting controls, 30 kVA transformer, 100 amp breaker .
- Issued Jan 6, 2026
1 units
Addition and/or Alteration · FOR THE ERECTION OF SWITCHGEARS AND GENERATORS ON CONCRETE PADS AND ASSOCIATED WORK TO REPLACE SUMP PUMPS AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP WORK.
- Issued Dec 3, 2025
—
New Construction · Electrical Permit for combo SP-2025-001317
- Issued Dec 2, 2025
Addition and/or Alteration · Recreational building renovations/ expansion. Including a new PECO utility transformer and incoming service. Including all new Fire alarm equipment and system. In accordance with NFPA 72 2016 & the Philadelphia Fire code 2018
- Issued Nov 19, 2025
Addition and/or Alteration · Installation of new 100amp, 240/120v, 1-Phase service / panel at Pennovation Works Off-Site Parking Lot.
- Issued Nov 19, 2025
Addition and/or Alteration · Replacing 300 existing light fixtures (one for one) with no new conduit or wiring. Also upgrading the conduit and wiring in the elevator machine room. ******************************* ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC AND PER PLANS.
- Issued Oct 23, 2025
Addition and/or Alteration · INSTALL 23 RELAY MODULES FOR HVLS FANS SHUTDOWNS. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC, 2016 NFPA AND PER PLANS.
- Issued Oct 17, 2025
Addition and/or Alteration · Provide temporary 13.2KVA high voltage from PECO service manhole service access and PECO selector switch and run aerial cable on (11) telephone poles to new 4 section 1000 amp 13.2 to 480v Switchgear. In addition, install 8-way telecommunication duct bank around the perimeter of the property as per 2017 NEC.
- Issued Oct 14, 2025
Addition and/or Alteration · Install 23 High Velocity fans in warehouse area . ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC. **SEPARATE FIRE ALARM PERMIT WILL BE REQ'D FOR THE FIRE ALARM WORK**
- Issued Oct 9, 2025
Addition and/or Alteration · Install 1000kva transformer for future use. All work to be done according to the 2017 NEC.
- Issued Oct 6, 2025
Addition and/or Alteration · INSTALL LIGHTING FIXTURES, LIGHTING CONTROL, GFCI RECEPTACLE OUTLETS AND REPLACE FIRE ALARM DEVICES TO RESTROOM AREA. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC.
- Issued Sep 29, 2025
Addition and/or Alteration · Install branch circuits, disconnects and VFDs for mechanical equipment; two light fixtures; one new receptacle ,fire alarm. ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC,2016 NFPA-72.
- Issued Sep 18, 2025
1 units
Addition and/or Alteration · FOR THE INSTALLATION OF STRUCTURAL STEEL TO SUPPORT THE EXISTING ROOF STRUCTURE. FOR USE AS PREVIOUSLY APPROVED. AS PER APPROVED PLANS. ************SEPARATE PERMITS FOR ANY OTHER WORK. **********************************
- Issued Sep 17, 2025
Addition and/or Alteration · New lighting and receptacles on mezzanine platform . ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC.
Track this owner
We'll flag their next deal, permit, or filing — usually before the neighbors know.
Entities are grouped by a normalized name from the public record; a separate legal entity per building is common, so some portfolios span several related names. Sources: Phila. Dept. of Records (deeds), L&I (permits & violations), Dept. of Revenue (tax delinquencies), reflecting the record as of our last weekly ingest. Verify independently before relying on it.
Last generated August 1, 2026.