THE INDEX: 64 17 · week of Jun 29permits soft, openings quiet, deal ledger quiet

The Philadelphia Index

Entity File · The Public Record

Contractor

Charles H Macdonald Electric I

15 permits

Records on file
15

Built (as contractor)

15 entries

  1. Issued Jun 15, 2026

    3401 Grays Ferry Ave

    Addition and/or Alteration · Installation of a 100amp feed 480 volt from adjacent building ECR to transit garage, to a 45kva transformer 480/208-120 volt mounted in garage. This transformer will feed a 200 amp main breaker panel 30 circuit. Mount (4) blink MQ 200 Fleet chargers located in parking garage 5 feet from entrance. Install (4) 50amp 2pole circuit breakers to feed charger stations. Install submetering for this panel. All work to be done according to the 2017 NEC and per approved plans.

  2. Issued Apr 30, 2026

    6226 Elmwood Ave

    Addition and/or Alteration · CMD will install cameras throughout the school.

  3. Issued Apr 30, 2026

    2039 Cherry St

    Addition and/or Alteration · INSTALL NEW PANELS, UTILIZING THE EXISTING BACK BOXES AT THE PANEL LOCATIONS A, B, C, D, AND F. A NEW PANEL WITH A NEW BACK BOX AT PANEL LOCATION E. FIELD EVALUATION AND INSPECTION IS REQUIRED.NRTL SHALL PASS/FAIL THE REFURBISHED EQUIPMENT INSTALLATION. PER NEC17 110.21(A)(1) & (A)(2).." A FIELD EVALUATION BODY SHALL CERTIFY THE PANELS. ELECTRICAL CONTRACTOR SHALL UPLOAD THE NRTL CERTIFICATION ***ALL WORK PER APPROVED PLANS***

  4. Issued Mar 20, 2026

    1600-18 Arch St

    Addition and/or Alteration · Alteration of First Floor Lobby and and 20th floor roof-top patio, to include furnishing and installing: a new power panelboard and transformer per drawings E320, E321, and E600; wiring devices per drawing E301 and E320; and installation of light fixtures and lighting control devices per drawings E301 and E320 as per 2017 NEC. Light fixtures and lighting control devices furnished by the owner.

  5. Issued Mar 13, 2026

    301 S Broad St

    Addition and/or Alteration · Install new electrical wiring to serve the installation of lighting, switches, and a new receptacle in the laundry closet. Relocate one (1) existing duplex receptacle to accommodate the installation of a built-in China closet. All work to be done according to the 2017 NEC and per approved plans.

  6. Issued Feb 20, 2026

    1700-20 Benjamin Franklin Pkwy

    Addition and/or Alteration · Installation of light fixtures and receptacles in the lobby and bathrooms 1st floor. All work to be done per plans. 1 Horn and strobe relocated in the lobby, per plans

  7. Issued Dec 8, 2025

    201 N 17th St

    Addition and/or Alteration · Replacement of 24 sconces and 20 chandeliers at existing j-box locations in meeting rooms, like for like, no wiring.

  8. Issued Oct 28, 2025

    3400 Market St

    Addition and/or Alteration · INSTALL NEW 200 AMP SUBPANEL. INSTALL CONDUIT AND WIRING FROM SUBPANEL TO POWER THE INSTALLATION OF THREE 4 HEAD POLE LIGHTS. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC.

  9. Issued Sep 22, 2025

    1900 John F Kennedy Blvd

    Addition and/or Alteration · Install new transformer sections in Olson Triplex transformer 1500kva cu copper Disconnect temporary transformer from primary. Provide connection to existing distribution via buss connection. Provide new primary conductors to line side of transformer as required into existing switchgear. Test transformer cables etc. Energize new transformer connected to existing switchgear. Provide 750kw temporary generator and cabling and cable generator to separated distribution section and back feed secondary

  10. Issued Aug 29, 2025

    3501 Chestnut St

    Addition and/or Alteration · Install new light fixtures and new power devices as shown on electrical drawings and as per 2017 NEC. Install new fire alarm devices as shown on fire alarm drawings and as per 2016 NFPA 72.

  11. Issued Aug 22, 2025

    301 S Broad St

    Addition and/or Alteration · MacDonald Electric will furnish and install new light fixtures as shown on drawing E3002.1 MacDonald Electric will furnish and install new power devices as shown on drawing E3002.1 ***NO FIRE ALARM***

  12. Issued Aug 19, 2025

    5700-30 City Ave

    Addition and/or Alteration · Furnish and install new power devices as shown on the electrical drawings Furnish and install new lighting fixtures and lighting controls as shown on the electrical drawings. Relocate fire alarm devices as required for this project to new locations in room as shown on the drawings. . ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC.

  13. Issued Aug 4, 2025

    3624 Market St

    Addition and/or Alteration · REMOVE OLD GENERATOR AND INSTALL 100 KW 480/277 VOLT 3 PHASE GENERATOR IN THE SAME LOCATION. THE EXISTING TRANSFER SWITCH WILL REMAIN. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC AND PER PLANS.

  14. Issued Aug 1, 2025

    3151 Market St

    Addition and/or Alteration · Fire Alarm system rough in and installation to be tied into existing building fire alarm system as per 2016 NFPA 72.

  15. Issued Jul 14, 2025

    440 N Broad St

    Addition and/or Alteration · New receptacles and data drops within renovated area. Power and data is served from existing sources located in adjacent storage room. New lighting and lighting controls are provided within the renovated area as well. Permit is for telecommunications and wiring for new lighting. ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC. **NO FIRE ALARM ON THIS PERMIT** AMENDMENT: Remove restroom portion from scope of work .See approved drawings.

Track this owner

We'll flag their next deal, permit, or filing — usually before the neighbors know.

Entities are grouped by a normalized name from the public record; a separate legal entity per building is common, so some portfolios span several related names. Sources: Phila. Dept. of Records (deeds), L&I (permits & violations), Dept. of Revenue (tax delinquencies), reflecting the record as of our last weekly ingest. Verify independently before relying on it.
Last generated August 1, 2026.