Records on file
67
First filed Jul 18, 2025Last activity Jul 8, 2026

On the record

Distress signals the city holds against this parcel — back taxes, open code violations, and unsafe designations.

Clear

No open violations or delinquencies on record for this address.

The docket

67 entries

  1. Issued Jul 8, 2026

    Permit issued — Addition and/or Alteration

    Install grounding and temp power feeds from temp portable generators for the MLB All Star Game Street Event. Temporary power install is for less than 90 Days. · contractor: HATZEL & BUEHLER INC

  2. Issued Jul 8, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  3. Issued Jul 7, 2026

    Permit issued — Addition and/or Alteration

    (2) Temporary Generators For the Allstar Game · contractor: HATZEL & BUEHLER INC

  4. Issued Jun 30, 2026

    Permit issued — Addition and/or Alteration

    Install (4) temp generators (2) are 320 kw and the other (2) 70 kw for a concert · contractor: EAGLE I ELECTRIC INC

  5. Issued Jun 29, 2026

    Permit issued — Addition and/or Alteration

    Hook up 12 generators for All Star game as per NEC. tThe generators are for tv networks to broadcast all-star baseball game on July 14,2026. This will power Broadcast trucks for FOX, MLB, Netflix, Game press and some office trailers for sportscasters. · contractor: MICHAEL GITLIN

  6. Issued Jun 24, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL.

  7. Issued Jun 22, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. Streets Department permit is required for street closure prior to the start work if applicable.

  8. Issued Jun 22, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    1.4 g close prox. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  9. Issued Jun 18, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. Streets Department permit is required for street closure prior to the start work if applicable.

  10. Issued Jun 17, 2026

    Permit issued — Addition and/or Alteration

    Hook up single 250kw portable generator as per the NEC. Provide standby electrician for Phillies game dated 6/21/26. This is backup power for Peacock broadcast trailer. · contractor: MICHAEL GITLIN

  11. Issued Jun 15, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  12. Issued Jun 11, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. Streets Department permit is required for street closure prior to the start work if applicable.

  13. Issued Jun 5, 2026

    Permit issued — Addition and/or Alteration

    Furnish and install Fire Alarm System to Ballpark Event Tent. All work to be done according to the 2017 NEC, 2016 NFPA 72 and per approved plans. · contractor: HATZEL & BUEHLER INC

  14. Issued Jun 2, 2026

    Permit issued — Addition and/or Alteration

    Hook up 250 kw portable generator as per NEC for standby power for TBS broadcast truck for phillies game on June 2, 2026. set up is June 1st 2026 Provide standby electrician. · contractor: MICHAEL GITLIN

  15. Issued May 15, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    1.3 g Fireworks Display. 5" Max shell. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  16. Issued May 15, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    1.4 close prox. pyro for graduation. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  17. Issued May 7, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. Streets Department permit is required for street closure prior to the start work if applicable.

  18. Issued Apr 27, 2026

    Permit issued — Addition and/or Alteration

    INSTALL GROUNDING FOR TEMPORARY GENERATORS used to power lighting and receptacles in tents used for A block party at CITIZENS BANK PARK ON MAY 13 AND 14 2026 · contractor: LCN PARTNERS, INC.

  19. Issued Apr 20, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    1.4g close proximity pyro. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  20. Issued Apr 9, 2026

    Permit issued — Addition and/or Alteration

    Hook up a 500KW portable generator for backup power as per NEC for backup power on 4/19/26 for NBC broadcast truck. set up is 4/18/26. · contractor: MICHAEL GITLIN

  21. Issued Apr 9, 2026

    Permit issued — Addition and/or Alteration

    Hook up temporary Generator 500KW as per NEC for Phillies game on 4/14/26 for TBS broadcasting. Set up is on 4/12/26 game is 4/14/26. Generator is for backup power for broadcast truck. · contractor: MICHAEL GITLIN

  22. Issued Apr 9, 2026

    Permit issued — Addition and/or Alteration

    FOR THE LEGALIZATION/ERECTION OF PERMANENT TENT STRUCTURE WITH MAXIMUM OCCUPANCY OF 300 PERSONS. SEPARATE PERMITS REQUIRED FOR ANY MEP WORK. *AUTOMATIC SMOKE DETECTION SYSTEM REQUIRED AS PER BBS VARIANCE UNDER MI-2026-000319.* · contractor: LF Driscoll Company LLC · 1 units

  23. Issued Mar 28, 2026

    Permit issued — New construction, addition, GFA change

    For the erection of a permanent, detached tent structure accessory to the existing stadium structure. Size and location per plan. · contractor: BALLARD SPAHR LLP

  24. Issued Mar 23, 2026

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. IF TENT IS NOT READY FOR INSPECTION TO INCLUDE ELECTRICAL COMPONENTS, AN ADDITIONAL WILL BE APPLIED FOR ANY AFTER HOURS INSPECTION WITH POSSIBLE ISSUANCE OF CODE VIOLATION NOTICES.

  25. Issued Mar 13, 2026

    Permit issued — Fireworks / Pyrotechnics Display

    All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  26. Issued Mar 4, 2026

    Permit issued — Addition and/or Alterations

    EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate (8) sprinkler heads to accommodate alterations · contractor: Oliver Sprinkler Co., Inc.

  27. Issued Mar 2, 2026

    Permit issued — Addition and/or Alterations

    FOR THE INSTALLATION OF 153 NEW PENDENT SPRINKLERS AND TWO (2) STANDPIPES TO AN EXISTING FIRE SUPPRESSION SYSTEM COMPLYING WITH NFPA 13 THROUGHOUT THE BUILDING. AS PER APPROVED PLANS. ALL WORK SHALL BE PERFORMED BY A FIRE SUPPRESSION CONTRACTOR LICENSED BY THE CITY OF PHILADELPHIA. ALL WORK SHALL BE DONE IN ACCORDANCE WITH APPROVED PLANS/HYDRAULIC CALCULATIONS. · contractor: Oliver Sprinkler Co., Inc.

  28. Issued Feb 24, 2026

    Permit issued — Addition and/or Alteration

    PROVIDE GROUNDING AND BONDING TO GENERATOR FOR SPECIAL OLYMPICS POLAR PLUNGE AT CITIZENS BANK PARK · contractor: ROBERT J MCDEVITT

  29. Issued Feb 18, 2026

    Permit issued — Addition and/or Alterations

    EZ KITCHEN FIRE SUPPRESSION- For the installation of New Wet Chemical Kitchen Fire Suppression System as per attached standard. Deviations from these standards require submission of construction and site plans. Install 3 Gallon Ansul R102 Kitchen FSS in Hall of Fame Bistros · contractor: Joseph F Spaeder

  30. Issued Feb 17, 2026

    Permit issued — Addition and/or Alteration

    STATEMENT OF WORK: FIBER CABLING: • Provide labor to install 288-strand singlemode non-armored ribbon fiber optic cable from the Head End to Comm Rooms 3.12.04, 3.37.03, 5.37.04, 5.08.03, 5.22.04 and North Tunnell IDF. • Provide labor to install of 6-strand fiber/conductor composite cable from Comm Rooms 3.12.04, 3.37.03, 5.37.04, 5.08.03, 5.22.04 and North Tunnell IDF as required out to twenty-seven (27) remote locations. • Provide labor to install the following equipment as required to fa · contractor: BLUESTONE COMMUNICATIONS INC

  31. Issued Feb 17, 2026

    Permit issued — Temporary Tents and Canopies

    TENTS FOR POLAR PLUNGE AS PER PLAN AND PHILADELPHIA FIRE CODE. NO ENCROACHMENT IN THE PUBLIC RIGHT of WAY. STAGE IS NOT PART OF THIS PERMIT. ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING.

  32. Issued Feb 10, 2026

    Permit issued — Addition and/or Alterations

    FOR THE INSTALLATION OF TWO (2) TYPE 1 COMMERCIAL KITCHEN HOOD (10'-0") EACH WITH ASSOCIATED DUCTWORK, FANS AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR ELECTRICAL AND FIRE SUPPRESSION WORK. **IMC 2018** · contractor: Joseph F Spaeder

  33. Issued Feb 10, 2026

    Permit issued — Addition and/or Alterations

    EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate (208) sprinklers to accommodate changes in layout · contractor: Oliver Sprinkler Co., Inc.

  34. Issued Feb 4, 2026

    Permit issued — Addition and/or Alterations

    FOR INSTALLATION OF HVAC APPLIANCES, EQUIPMENT, DUCTWORK AND REGISTERS/DIFFUSERS PER APPROVED PLANS AND MANUFACTURER'S SPECIFICATIONS. · contractor: HERMAN GOLDNER CO INC

  35. Issued Jan 27, 2026

    Permit issued — Addition and/or Alteration

    Furnish and Install Power, EWH disconnects, and Lighting Per Plans and 2017 NEC. · contractor: HATZEL & BUEHLER INC

  36. Issued Jan 27, 2026

    Permit issued — Addition and/or Alteration

    FOR LEVEL II ALTERATIONS WITH NO CHANGE OF OCCUPANCY. SEPARATE PERMITS REQUIRED FOR MECHANICAL, ELECTRICAL, PLUMBING AND FIRE SUPPRESSION WORK. · contractor: LF Driscoll Company LLC · 1 units

  37. Issued Jan 26, 2026

    Permit issued — Alterations

    Install new floor drains for Bistro's, new water lines, water heater's and 2 sinks · contractor: HERMAN GOLDNER CO INC

  38. Issued Jan 20, 2026

    Permit issued — Addition and/or Alterations

    EZ PERMIT SPRINKLER RELOCATION (NFPA 13)- For the relocation of sprinkler heads as per attached standards. Deviations from these standards require submission of construction and site plans. Relocate (54) sprinklers to accommodate changes to owner's suite and restrooms · contractor: Oliver Sprinkler Co., Inc.

  39. Issued Jan 19, 2026

    Permit issued — Addition and/or Alteration

    FOR LEVEL I ALTERATIONS (REMOVAL AND REPLACEMENT OF TOPPING SLABS AND DRAINS) AT SPECIFIED LOCATIONS THROUGHOUT THE EXISTING GROUP A-5 OUTDOOR BASEBALL STADIUM (CITIZENS BANK PARK) AS PER APPROVED PLANS AND IN ACCORDANCE WITH 2018 IEBC. SEPARATE PERMITS TO BE OBTAINED FOR ALL OTHER WORK. · contractor: LF Driscoll Company LLC · 1 units

  40. Issued Jan 16, 2026

    Permit issued — Addition and/or Alteration

    FOR LEVEL II ALTERATIONS WITH NO CHANGE IN OCCUPANCY. SEPARATE PERMITS REQUIRED FOR MECHANICAL, ELECTRICAL, PLUMBING AND FIRE SUPPRESSION WORK. · contractor: LF Driscoll Company LLC · 1 units

  41. Issued Jan 14, 2026

    Permit issued — New Construction or Additions

    Install new storm water piping for new team store addition 5 roof drains · contractor: HERMAN GOLDNER CO INC

  42. Issued Jan 13, 2026

    Permit issued — Addition and/or Alterations

    FOR THE INSTALLATION OF REGISTERS, DIFFUSERS AND APPLIANCES WITH ASSOCIATED DUCTWORK. APPLIANCES TO BE INSTALLED IN ACCORDANCE WITH THE MANUFACTURER’S SPECIFICATIONS. ALL WORK TO BE DONE PER APPROVED PLANS. IF FIELD CONDITIONS VARY CONTACT DESIGN ENGINEER PRIOR TO THE START OF ANY WORK. · contractor: HERMAN GOLDNER CO INC

  43. Issued Jan 9, 2026

    Permit issued — Alterations

    Level Hall of Fame Club Suite renovations Fixture replacement in gang restrooms · contractor: HERMAN GOLDNER CO INC

  44. Issued Dec 30, 2025

    Permit issued — Addition and/or Alterations

    FOR INSTALLATION OF HVAC APPLIANCES, EQUIPMENT, DUCTWORK AND REGISTERS/DIFFUSERS PER APPROVED PLANS AND MANUFACTURER'S SPECIFICATIONS. · contractor: HERMAN GOLDNER CO INC

  45. Issued Dec 15, 2025

    Permit issued — Addition and/or Alteration

    LEVEL II ALTERATIONS (NO CHANGE OF OCCUPANCY) FOR RENOVATIONS TO OWNER'S SUITE AND RESTROOMS WITHIN AN EXISTING OUTDOOR BASEBALL STADIUM AS PER APPROVED PLANS. *2018 IEBC REVIEW* **SEPARATE PERMIT REQUIRED FOR ANY WORK** · contractor: LF Driscoll Company LLC · 1 units

  46. Issued Dec 4, 2025

    Permit issued — Addition and/or Alteration

    Furnish and Install , receptacles , panels and Lighting . ALL WORK IS TO BE DONE ACCORDING TO APPROVED DRAWINGS-2017 NEC. · contractor: HATZEL & BUEHLER INC

  47. Issued Nov 19, 2025

    Permit issued — Foundation

    FOR FOUNDATIONS AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR STRUCTURE. *NO EXCAVATION GREATER THAN 5FT, OTHERWISE SEPARATE EXCAVATION PERMIT REQUIRED.* · contractor: LF Driscoll Company LLC

  48. Issued Nov 19, 2025

    Permit issued — Addition and/or Alteration

    FOR THE ERECTION OF AN ADDITION TO EXPAND MERCANTILE AND LEVEL II ALTERATIONS TO INCLUDE NEW PARTITIONS, DOORS, FURNISHINGS, FINISHES AS PER APPROVED PLANS. SEPARATE PERMITS REQUIRED FOR MEP AND FIRE SUPPRESSION WORK. · contractor: LF Driscoll Company LLC · 1 units

  49. Issued Nov 13, 2025

    Permit issued — EZ Interior Non-Load-Bearing Wall Demo.

    For minor construction work at the subject property in accordance with all applicable provisions of the Philadelphia Code, all references codes and standards, and the attached EZ Standard, where included. Deviation from this standard shall result in permit revocation. A separate permit from the Philadelphia Department of Streets is required for any sidewalk and street closures. All means of pedestrian protection required at the site in accordance with the Philadelphia Building Code Chapter 33 sh

  50. Issued Oct 30, 2025

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. IF TENT IS NOT READY FOR INSPECTION TO INCLUDE ELECTRICAL COMPONENTS, AN ADDITIONAL WILL BE APPLIED FOR ANY AFTER HOURS INSPECTION WITH POSSIBLE ISSUANCE OF CODE VIOLATION NOTICES.

  51. Issued Oct 22, 2025

    Permit issued — New construction, addition, GFA change

    FOR THE ERECTION OF A ONE (1) STORY ADDITION ATTACHED TO AN EXISTING DETACHED STRUCTURE; SIZE AND LOCATION AS SHOWN IN PLANS. · contractor: BALLARD SPAHR LLP

  52. Issued Oct 21, 2025

    Permit issued — Addition and/or Alteration

    LEVEL II ALTERATIONS (NO CHANGE OF OCCUPANCY) FOR STRUCTURAL AND NON-STRUCTURAL DEMOLITION WITHIN AN EXISTING SPORTS STADIUM FOR FUTURE ADDITION AS PER APPROVED PLANS. *2018 IEBC REVIEW* · contractor: LF Driscoll Company LLC · 1 units

  53. Issued Oct 14, 2025

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. IF TENT IS NOT READY FOR INSPECTION TO INCLUDE ELECTRICAL COMPONENTS, AN ADDITIONAL WILL BE APPLIED FOR ANY AFTER HOURS INSPECTION WITH POSSIBLE ISSUANCE OF CODE VIOLATION NOTICES.

  54. Issued Oct 13, 2025

    Permit issued — EZ Interior Non-Load-Bearing Wall Demo.

    For minor construction work at the subject property in accordance with all applicable provisions of the Philadelphia Code, all references codes and standards, and the attached EZ Standard, where included. Deviation from this standard shall result in permit revocation. A separate permit from the Philadelphia Department of Streets is required for any sidewalk and street closures. All means of pedestrian protection required at the site in accordance with the Philadelphia Building Code Chapter 33 sh

  55. Issued Oct 7, 2025

    Permit issued — Addition and/or Alteration

    Temporary on site wiring for hook up of twin 500KW portable generators for Phillies play-off series as per NEC dates 10/2/25 thru 10/11/25. Generator to be used for backup power for 3 broadcast trucks for TBS network. provide standby 2 stand by electricians for games. ALL WORK TO BE DONE ACCORDING TO THE 2017 NEC. · contractor: MICHAEL GITLIN

  56. Issued Sep 30, 2025

    Permit issued — Fireworks / Pyrotechnics Display

    All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  57. Issued Sep 19, 2025

    Permit issued — Addition and/or Alteration

    Install (4) temp generators (2) are 320 kw and the other (2) 70 kw for event at Citizen Bank · contractor: EAGLE I ELECTRIC INC

  58. Issued Aug 25, 2025

    Permit issued — Addition and/or Alteration

    Hook up portable twin 100kw generator as per NEC for ESPN broadcast truck back up power for Hillies game August 31st and stand by electrician, · contractor: MICHAEL GITLIN

  59. Issued Aug 21, 2025

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. IF TENT IS NOT READY FOR INSPECTION TO INCLUDE ELECTRICAL COMPONENTS, AN ADDITIONAL WILL BE APPLIED FOR ANY AFTER HOURS INSPECTION WITH POSSIBLE ISSUANCE OF CODE VIOLATION NOTICES.

  60. Issued Aug 19, 2025

    Permit issued — Temporary Tents and Canopies

    ASSEMBLY USE TENT - LAWFUL OCCUPANCY SHALL BE AS POSTED - REMOVAL DATE ELECTRICAL PERMIT REQUIRED, UNLESS POWER IS PROVIDED THROUGH EXISTING EXTERIOR GROUND FAULT PROTECTED RECEPTACLES AND POWER CORDS ARE RATED EXTRA HEAVY DUTY WITH U. L. LABEL STATING SUCH RATING. NO COOKING OR HEATING PERMITTED WITH THIS APPROVAL. IF TENT IS NOT READY FOR INSPECTION TO INCLUDE ELECTRICAL COMPONENTS, AN ADDITIONAL WILL BE APPLIED FOR ANY AFTER HOURS INSPECTION WITH POSSIBLE ISSUANCE OF CODE VIOLATION NOTICES.

  61. Issued Aug 15, 2025

    Permit issued — Addition and/or Alteration

    Install (4) temp generators (2) are 320 kw and the other (2) 70 kw for event at Citizen Bank · contractor: EAGLE I ELECTRIC INC

  62. Issued Aug 12, 2025

    Permit issued — Temporary Tents and Canopies

    C#52619 INSTALLING ENCLOSED 20X40 TENT

  63. Issued Aug 5, 2025

    Permit issued — Fireworks / Pyrotechnics Display

    1.4 g pryo and flame. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

  64. Issued Jul 30, 2025

    Permit issued — Addition and/or Alteration

    Hook up 100KW portable generator as per NEC for broadcast truck stand by power for ESPN phillies game 07/23/25. · contractor: MICHAEL GITLIN

  65. Issued Jul 30, 2025

    Permit issued — Addition and/or Alteration

    Hook up portable Twin 100kw generator as per NEC for Phillies game Broadcast by ESPN on 8/2 and 8/3. backup power for broadcast truck. · contractor: MICHAEL GITLIN

  66. Issued Jul 21, 2025

    Permit issued — Addition and/or Alteration

    hook up portable generator 100kw as per NEC for phillies game on July 22, 2025. generator will be for backup power to broadcast trailer for TBS broadcast network. · contractor: MICHAEL GITLIN

  67. Issued Jul 18, 2025

    Permit issued — Fireworks / Pyrotechnics Display

    1.4 g close proximity pyro and flame. All effect shall adhere to the 2018 Philadelphia Fire Code and applicable NFPA referenced standards. These shall include but not limited to NFPA 1126,1123 and NFPA 160. The safe operation of all effects is the responsibility of the shooter. Permit approval is subject to a demo to the assigned Fire Code official.

Nearby on the record

Other addresses in 19148 with recent activity on the public record.

The 19148 dashboard →The Stadium District dashboard →Every recent record in 19148

Track this parcel

We'll flag the next deed, permit, or violation on the record here — usually before the neighbors do.

Sources: Phila. Dept. of Records (deeds), L&I (permits, licenses & violations), Dept. of Revenue (tax delinquencies). Data reflects the public record as of our last weekly ingest; last activity on file July 8, 2026. Verify independently before relying on it.